Plans for New Tunnel to Reduce Sewage Overflow in Rivers

Written by: Rachel Abraham, Kristine Lindal, Ali Rairigh, Emily Yager

Fort Wayne, Ind.—City Utilities will begin construction of the $240 million Three Rivers Protection and Overflow Reduction Tunnel project in 2017, according to Kelly Bajic, city utilities professional engineer, to reduce the amount of sewage discharged into the St. Marys and Maumee Rivers during storms.

According to a city 3RPORT and Tunnel Works release, the project responds to a federal mandate for the city to reduce combined sewer overflow from 100 billion to 100 million gallons by 2025.

Matthew Wirtz, deputy director of engineering for the city, said during heavy storms, the sewage system overflows and raw sewage mixed with rainwater flows into the river.

According to Bajic, the tunnel will have a capacity of 31 million gallons, although it will primarily be used for conveyance and not storage.

Wirtz said once the tunnel is constructed, the majority of the flow currently discharging into the river will drop into the tunnel.

The 5-mile tunnel will begin south of Foster Park and run to the existing sewage treatment plant on the Maumee River. According to Wirtz, they will drill 150 to 250 feet into the bedrock where the tunnel will run underneath downtown and around Foster Park. The tunnel will convey flows to the wet weather ponds located north of the Water Pollution Control Facility, according to Bajic.

Wirtz said the construction will take 4 to 5 years because they will have to bore the hole underground, come to the surface and connect the existing sewers.

According to Bajic, 13 drop shafts will be constructed to convey the flow from the near surface sewers down into the tunnel.

“The tunnel itself will be done in a few years, but then getting all the rest of that stuff done will take a couple more,” Wirtz said.

Robert Gillespie, associate professor of biology at IPFW, said he and a team of students have been helping the city monitor river water quality during intense events. According to Gillespie, there are some great students who are eager to work on the tunnel project, helping the city accomplish what they couldn’t do on their own.

Gillespie said once the tunnel is completed positive impacts on water quality could be seen after only one season.

Wirtz said in addition to improving river water quality, the tunnel will reduce street and basement flooding and help move water from homes to the treatment plant faster.

“We’ll still have problems in really large storms, but the more normal, small storms will provide much better protection,” Wirtz said.

“It’s trying to fix something that’s been a problem not only in our community but in a lot of midwest communities,” Bajic said. “There’s a lot of different communities that have combined sewer systems, so it’s not just Fort Wayne.”

According to Bajic, the project is currently in the design phase and the next step for the project is getting documents ready for the bidding process by the end of Fall 2016.

Riverbank Erosion and Transmission Corridor Project Delay Rivergreenway Trail Completion

Written by: Rachel Abraham, Kristine Lindal, Alexandria Rairigh

Fort Wayne, Ind.–A 1.2 mile stretch of the Rivergreenway neighboring IPFW cannot be completed until the city addresses riverbank erosion and Indiana Michigan Power finishes their transmission project

Riverbank erosion is an issue for the remaining trail between St Joe Center Road and East California Road, according to the most recent Rivergreenway project status report.

Dawn Ritchie, greenways manager for the city, said there are 400 linear feet of riverbank erosion on the 1.2 mile stretch of uncompleted trail. According to the report, the city must find a solution to the erosion before the trail can be completed.

“There’s nothing that has been done to shore up the riverbank or stop the erosion,” Ritchie said. “We’re talking about hundreds of thousands of dollars to fix this, and nobody has the money to do that, unfortunately.”

Robert Gillespie, university biology professor and an associate of the center, studies the degradation of aquatic communities. He participated in a sub-committee with city utilities that assessed a plan for possible impacts on areas of riverfront development.

Riverbank erosion is one such area, according to Gillespie. He said riverbank erosion will increase suspended solids, organic and inorganic materials that are suspended in water. This can be a problem for almost any aquatic organism because suspended solids get stuck in their gills and can cause suffocation, according to Gillespie. Gillespie said there are many places where erosion is a problem in the Fort Wayne area.

Indiana Michigan Power is currently working on a section of their Powering Up Northeast Indiana transmission project in the same area, according to Tracy Warner, principal communications consultant at the power company. The project is geared towards upgrading and enhancing the system and reliability, Warner said, because some of the equipment dates back to the 1940s.

The trail cannot be completed until the power company finalizes that part of the project, according to Ritchie.

The power company plans to begin construction on their transmission project next year. The project will take two years to complete. Warner said the company does not expect any issues from the erosion.

According to Warner, the power company strives to be a good neighbor to the greenway and the university and will continue to discuss the issue as the project progresses. “We’re looking forward to building this section,” he said.